The India solar wafer policy 2028 rewards early document discipline. This ALMM compliance checklist is a working aid, not legal advice.
Classify each as Section 63, net-metering, open-access or captive.
Why: The wafer rule turns on bid date for some routes and commissioning date for others.
When: Now.
Note the last bid-submission date, PPA date, award date and expected commissioning date.
Why: These determine whether grandfathering applies.
When: Now, and update after MNRE publishes the initial list.
Track MNRE notices closely.
Why: The cut-off is seven days after publication, so pipeline status can change within a week.
For bids after the cut-off, confirm the tender documents name List-I modules, List-II cells and List-III wafers. For earlier bids, confirm that the exemption basis is documented.
When: Before any bid or tender is issued.
Check the manufacturer, factory and model against the current MNRE lists, and note whether the item sits in the main list or a grandfathered list such as List-I(a).
Why: A listing in the wrong category may not satisfy your project.
When: At supplier selection and again before delivery.
Add representations on listing status, traceability and remedies if a supplier is delisted.
When: During contract drafting.
Compare supplier ramp-up with your commissioning schedule, since compliant wafer supply may be tight early on.
When: 12 to 18 months before commissioning.
Retain bid documents, PPAs, listing certificates and supplier declarations. Why: They prove which rules applied.
When: Throughout the process.
Align developers, EPC contractors, manufacturers and procurement on one dated source of truth.
When: Set up now, review quarterly.
The order does not relax DCR provisions under PM-KUSUM, PM Surya Ghar and the CPSU scheme Phase-II.
When: During project scoping.